Notice of Road Works
Rising Main Valve Chamber & MH Connection – Maryland Road/Hawkenbury Road/Forest Road
Installation of new Rising Main Valve Manhole Chambers in Maryland and Hawkenbury Road
Connection of new Rising Main Pipe in the existing Southern Water Manhole in Forest Road/Hawkenbury Road Junction.
Due to the location of the new Valve Chambers within the carriageway we will be installing full traffic Management via 2-Way and 4-Way Traffic Lights to maintain traffic flow within the affected areas.
Dates
- Adjacent to No 19 Maryland Road 12th to 19th August (2-Way Lights)
- Forest Road/ Hawkenbury Road junction 19th August to 2nd September (4-Way lights)
- Adjacent to No 20 Hawkenbury Road 3rd to 12th September (2-Way Lights)
Work will take place between the hours of 8:00am and 5:00pm